Steve Michaud Park Water Tower Rehabilitation Project

The City of Lakeville is planning for the rehabilitation of the water tower located in the Steve Michaud Park parking lot this summer. The project mainly consists of removing the paint of the tower and repainting. Once started, the project is scheduled to last a maximum of ten weeks, depending on weather.

There will be some light tower maintenance prior to this, including removing antennas from the tower to ensure the cellular signal is maintained during the project.

Project Timeline

  • June/July 2023: Antenna equipment will be temporarily removed from the water tower and placed on an antenna trailer in the parking lot
  • July 31, 2023: Construction begins
  • Early October 2023: Project completed

Contact Us

If you have any questions regarding the project, contact:

  • Brad Sipe, Short Elliott Hendrickson Inc. Project Manager: 651-765-2955 or by email
  • Shane Quade, City of Lakeville Utilities Superintendent: 952-985-2741 or by email