2024 Ipava Avenue and Indiana Avenue Improvements

The City of Lakeville is proposing to rehabilitate asphalt pavement on approximately 1.15 miles of Ipava Avenue from 185th Street (CSAH 60) to Indiana Avenue and Indiana Avenue from Ipava Avenue to Dodd Boulevard (CSAH 9). This project includes various methods of pavement rehabilitation, partial curb replacement, partial trail replacement, storm sewer repairs, as well as watermain upgrades at various fire hydrants and street valves.

Helpful Information

Project Timeline

  • Fall 2023: Preliminary engineering
  • Winter 2023/2024: Final design
  • Early spring 2024: Neighborhood meeting
  • March 2024: Anticipated award of the project
  • Spring/summer 2024: Construction begins
  • Summer/fall 2024: Construction complete